  The City of Virginia Beach is in full force replacing the sewage system on my street.  It’s part of the stimulus budget and the project is called “Sewer Defect Find and Fix” under the department  of Public Utilities and the budget is $3,000,000.  I think it’s money well spent.   However there many more repairs and upgrades that got the green light because of the government stimulus plan that seem like a waste.

     Oh by the way if want to know what a “Bridge to nowhere looks like” see the current Pacific Avenue Trail Extension Project, a boardwalk-style trail parallel to Pacific Avenue wrapping around the edge of Lake Holly.  I won’t mention how much but we could have had a couple of brand new or renovated school equipped with solar energy efficient or health care for indigenous families.  But hey, I’m not on the City Council so I’ll lock it up.

 Here’s a list of stimulus projects that got the green light:

Program Project Description Funding Required Jobs
CDBG Williams Farm Community Recreation Center $30,000,000 640
CDBG West Neck Creek Natural Area $528,000 12
CDBG Urban Tree Canopy Protection $3,750,000 76
CDBG Trail Repairs and Replacements $3,960,000 80
CDBG Thalia Creek Greenway $7,000,000 142
CDBG Tennis Court Replacements $1,800,000 38
CDBG Stumpy Lake Natural Area Phase I $2,500,000 51
CDBG Sportsplex Deferred Maintenance $2,300,000 47
CDBG Sidewalk Improvements $3,000,000 62
CDBG Seatack Community Center Expansion $2,200,000 48
CDBG Sandbridge Beach Hurricane Protection $18,000,000 65
CDBG Rosemont Forest Pump Station $8,000,000 83
CDBG Resort Beach Hurricane Protection $18,000,000 65
CDBG Replacement of Park Buildings $4,922,000 100
CDBG Recreation Center Security Lighting $300,000 17
CDBG Recreation Center Reception Area $350,000 29
CDBG Parking Lot Repairs and Replacements (11 sites) $4,450,000 92
CDBG Park Water Quality Improvements $2,000,000 41
CDBG Park Shelter Replacements $854,000 19
CDBG Park Bank Stabilization (11 parks) $1,650,000 35
CDBG Open Space Acquisition $17,677,600 355
CDBG North Virginia Beach 61st Street Pump Station $20,000,000 83
CDBG New Asphalt Trail Development $2,640,000 55
CDBG Neighborhood Park Renovations $720,000 16
CDBG Marshview Park Development $1,376,000 29
CDBG Lynnhaven Inlet Navigation Dredging $2,000,000 55
CDBG Lake Smith Natural Area Phase I $2,000,000 42
CDBG Kid’s Cove Playground Replacement $1,600,000 34
CDBG Kempsville Recreation Center Pool Area Repairs $400,000 24
CDBG Bow Creek Recreation Center Locker Room Renovations $250,000 23
CDBG 5K Loop Trail Facility $9,600,000 194
Energy Shore Drive/Pacific Avenue Solar Powered Flashing Lights $110,000 22
Energy Central Plant Pumps Modernization $225,000 13
Energy Central Plant Cooling Tower and Chiller Renovation $1,000,000 13
Public Safety K-9 Building $553,000 34
Public Safety Fire Station #9 Repairs $800,000 44
Public Safety Fire and Rescue Station – Thalia $6,365,000 102
Public Safety Creeds Training Simulation City $500,000 46
Public Safety Correction Center Roof $700,000 24
Public Safety Animal Control Facility $4,000,000 56
Schools Pupil Transportation Services $19,850,001 200
Schools Kellam High School $102,000,000 500
Schools Great Neck Middle School $62,549,253 500
Schools College Park Elementary $22,392,750 200
Streets/Roads Witchduck Road Phase I $27,487,000 24
Streets/Roads West Neck Road Interim – Phase I $1,400,000 14
Streets/Roads Virginia Beach Boulevard/ Constitution Drive $42,000 7
Streets/Roads Virginia Aquarium Elevated Pedestrian Crosswalk $4,900,000 84
Streets/Roads Traffic Signal Rehabilitation $11,000,000 104
Streets/Roads Traffic Signal Interconnect Installation $35,000 11
Streets/Roads Street Reconstruction $5,000,000 104
Streets/Roads Storm Water Infrastructure Rehabilitation / Princess Anne Plaza $6,000,000 104
Streets/Roads Shore Drive Corridor Improvements Phase IV $11,700,000 48
Streets/Roads Shore Drive Corridor Improvements Phase III $9,360,000 48
Streets/Roads Shore Drive Corridor Improvements Phase II $11,100,000 48
Streets/Roads Seaboard Road $7,299,000 48
Streets/Roads Princess Anne Road Phase VII $17,800,000 60
Streets/Roads Princess Anne Road Phase IV $43,900,000 48
Streets/Roads Primary System Infrastructure Improvements $3,500,000 54
Streets/Roads Pavement Maintenance Program Phase II $45,000,000 304
Streets/Roads Nimmo Parkway Phase V $61,700,000 520
Streets/Roads Major Bridge Rehabilitation $1,100,000 54
Streets/Roads Lynnhaven Parkway Phase XI $31,500,000 210
Streets/Roads Lynnhaven International $7,800,000 48
Streets/Roads Lesner Bridge Replacement $90,000,000 520
Streets/Roads Laskin Road Phase I $76,000,000 365
Streets/Roads Independence Boulevard/ Ewell Road $10,000 12
Streets/Roads Holland Road Phase VI $45,000,000 304
Streets/Roads Godspeed Road $585,000 14
Streets/Roads First Colonial Road/ Old Donation Parkway $75,000 7
Streets/Roads Elbow Road/Indian River Road $850,000 14
Streets/Roads Constitution Drive Extended $9,176,912 48
Streets/Roads Citywide Streetlight Upgrade $500,000 54
Streets/Roads Buckner Boulevard Extended $2,421,000 26
Streets/Roads Bonney Road/Kentucky Avenue $1,500,000 14
Streets/Roads Baker Road $3,225,000 26
Streets/Roads Avalon Avenue $1,650,000 14
Water Stumpy Lake Dam and Spillway Repairs $1,930,000 24
Water Silina Corvette Pump Station #511 $500,000 15
Water SA #403 Arrowhead Susquehanna Sanitary Sewer Rehabilitation Phase 1 $2,800,000 37
Water Regency Apartments Pump Station #260 $1,000,000 18
Water Public Utilities Public Access Renovations – Building 2 $300,000 15
Water Landstown Yard Improvements $55,000,000 71
Water Lake Edward West Pump Station #343 $1,000,000 19
Water Green Run/Crimson Holly Pump Station #549 $1,000,000 20
Water Green Run Garden Pump Station #547 $1,500,000 20
Water College Park Providence Road Pump Station #425 Abandonment and SS Realignment $2,800,000 30